Germany The TAR MS sets out requirements for the installation, operation and modification of customer facilities connected at the grid connection point to a electricity system operator’s medium-voltage grid (consumption and generation installations, storage facilities and hybrid installations).
Technical Rules for connecting customer facilities to the Medium-Voltage grid and their operation (“TAR MS” (TCR Medium Voltage))
The notified draft contains amendments to individual sections and new sections of the application rule VDE-AR-N 4110 (from 2022, notified under No. 2022/0879/D). The application rule VDE-AR-N 4110 is being revised to introduce the requirements and evidence for system-supporting properties and the provision of instantaneous reserve by customer facilities on the medium voltage grid.