2022/0204/GR
EC/EFTA
GR Greece
  • B00 - CONSTRUCTION
2022-07-08
2022-04-20

Public Works and Studies, Floor gullies, not odour-trap

Approval of eighty-two (82) Hellenic Technical Specifications (HTS), the application of which is mandatory in all public works and studies.

ELOT TS 1501-04-04-04-02 Floor gullies, not odour-trap

Approval of eighty-two (82) Hellenic Technical Specifications (HTS), the application of which is mandatory in all public works and studies.

ELOT TS 1501-04-04-04-02 Floor gullies, not odour-trap
The purpose of this Technical Specification is to lay down the requirements for the materials and construction of floor gullies, which are connected to the rainwater drainage network without an odour-trap.